Earthworks / Plant Site Development
- Vale Inco Project
Long Harbour, NL
Description: This project
began in July 2009, with Plant Site first concrete
started June 2010, and has an approximate value
of $100,000,000.
The work is located on a greenfield site and consists of a Main Access Road to Site from Route 202,
a Plant to Port Pipeline Corridor... (More...)
|
 |
Construction of Torbay Bypass Road
Torbay, NL
Description: Completed in September 2009 and valued at approximately $13 million, this project consisted of the
construction of the Torbay Bypass Road
from Torbay Road to its intersection with the Pouch Cove Highway near Picco's Brook.
The work on this highway included clearing, grubbing,
drilling and blasting of approximately 1.1 million
tonnes of rock... (More...)
|
 |
Wuskwatim Generating Station
Wuskwatim, Manitoba
Description: Pennecon's Heavy Civil Division completed phase 1 of
the Wuskwatim Generating Station project in Manitoba in March 2009.
The project was developed by Wuskwatim Power Limited Partnership, a legal entity involving Manitoba Hydro and the Nisichawayasihk Cree Nation. (More...)
|
 |
Highway 97 Sintich Road to Continental Way Overpass
Prince George, British Columbia
Description: In April 2009, Pennecon Heavy Civil Ltd. was awarded the $12 million contract for the
construction of the Highway 97 Sintich Road to Continental way Overpass in Prince
George, B.C.
The construction consists of upgrading Hwy 97 to a four lane standard with the addition
of two travel lanes and a median over 3.5 km. (More...)
|
 |
Hixon Creek Bridge
Prince George, British Columbia
Description: In January 2008, Pennecon Heavy Civil Ltd. was awarded the $5.9 million contract for
the construction of the four lane Hixon Creek Bridge and 700 meters of associated
approaches, located approximately 35 minutes south of Prince George, B.C. (More...)
|
(More Heavy Civil Division Projects...)
 |
Long Harbour Processing Plant - Concrete Production
Long Harbour, NL
Description: In February 2010, Capital Ready Mix was awarded a contract from Vale Inco Newfoundland & Labrador Ltd to
supply, erect and operate two Concrete Batch Plants at the site of Vale's Long Harbour Processing Plant...(More...)
|
 |
Reconstruction of the Stanley Park Seawall
Vancouver, BC
Description: The general contractor for the reconstruction
of the Stanley Park seawall is Graham Construction. This rebar project
started in August 2010, with completion expected in Oct 2010.
|
 |
Memorial University - Parking Garage
St. John's, NL
Description: Pennecon Concrete is supplying and pumping 9000m3 of concrete for the new
Memorial University of Newfoundland Parking Garage.
|
 |
Nanaimo Airport Terminal Expansion
Nanaimo, BC
Description: This project is part of the long-term infrastructure upgrade of the Regional District of Nanaimo.
It is being implemented in several phases... (More...)
|
 |
Husky Searose
Offshore, NL
Description: Pennecon Concrete, in conjunction with
Pennecon Energy Marine Base, crushed and loaded 160,000 tonnes of rock
aboard the Seahorse which was used to protect pipelines offshore.
|
(More Concrete Division Projects...)
 |
INCO Hydromet Facility
Argentia, NL
Trade: Electrical, instrumentation
Description: Pennecon Energy provided module fabrication support and its expertise for this Voisey’s Bay Nickel Company project.
|
 |
TransOcean Henry Goodrich Inspection Survey and Refit (mechanical, hydraulic, structural and electrical
Bull Arm, NL
Trade: Coatings, inspection, electrical, structural, instrumentation, piping, hydraulic, mechanical overhaul and testing, NDT testing and 3500 HP thruster motor electrical, anode replacement, top drive overhauls and five year inspection
Description: Owned by TransOcean Canada Co., this
project required Pennecon's expertise for exterior work, anode replacement,
top drive overhauls, motor rewinding, painting, mechanical inspection,
NDT testing, and 3500 HP motor electrical, mechanical overhaul, and testing.
A five year inspection was also required.
|
 |
Terra Nova Turnaround
Rotterdam, The Netherlands
Trade: Hydraulic
Description: This major project for Pennecon Energy had numerous phases. On the voyage to Rotterdam, we did a complete removal of main transfer deck using clamshell cutters. Once we reached The Netherlands, we prepared a flushing procedure for a complete offshore flushing of the water injection pump lubrication system, then performed a complete re-certification of all pressure vessels aboard the Terra Nova FPSO.
|
 |
Abitibi Consolidated
Grand Falls, NL
Trade: Upgrades, refits, installations
Description: In this 2002 project for Abitibi Consolidated, we installed a hydraulic governor system during a refit of the Grand Falls Mill. During the refit, we also completed chemical cleaning, hydrotesting, and hot oil flushing of the hydraulic governor piping system.
|
(More Energy Division Projects...)
 |
Adam's
Pond Subdivision
Paradise, NL
Description: This development involves over 250
lots and has been ongoing since 2004. Approximately 150 lots are left
to develop.
|
 |
Elizabeth Park Subdivision
Paradise, NL
Description: This development involves over 800
lots and has been ongoing since 1997. Approximately 300 lots are left
to develop.
|
 |
Forest
Hills Subdivision
Conception Bay South, NL
Description: This development involved approximately
175 lots and was completed over a five year period. |
 |
Octagon
Industrial Park
Paradise, NL
Description: This development
involves over 80 acres and has been ongoing since 2000. Approximately
10 acres of land remain.
|
|
| |
|
|
 |
|