Description:
In January 2008, Pennecon Heavy Civil Ltd. was awarded the $5.9 million contract for
the construction of the four lane Hixon Creek Bridge and 700 meters of associated
approaches, located approximately 35 minutes south of Prince George, B.C.
The project was completed in two phases; the first to construct access roads to the bridge
site for pile driving equipment and to commence with the construction of the new bridge
and associated road works.
The second phase of the project saw the demolition of the
existing bridge, foundation works, abutment construction, girder erection and bridge
deck.
The project was successfully completed in November 2009, despite severely cold weather
conditions during access road construction.
|